MANA BADI NADU NEDU: Summer instructions for completion of Works

 Circular  .No. 2045894/MBNN/2023       Dated .13/04/2023

Sub:Mana  Badi  Nadu  Nedu,  Phase-I1-  Ensure  that  the  instructions  should   be followed while   implementing  the  program   – issued.

Ref:    G.O.Ms.no.119, Dt.22.06.2022  of the  School  Education   (Program-II).  Government  of Andhra  Pradesh.

Government  vide  reference   read  above,  accorded   Administrative   sanction   for improving    Infrastructure   facilities    in  22,344    Schools  and  other   Educational  institutions with  a total   budget   outlay   of  Rs.8000   Crores  under   Phase  2 of  Mana  Badi  Nadu  Nedu program.

It is proposed  to  complete   all the  Nadu  Nedu  components  and keep  the  schools  ready by 12th June 2023.  During  the  coming  two  months  the  following   activities   will  be started.

I.   Roof repairs  and Ceiling  repairs.

II.  Supply  and installation    of furniture. 

III. Major  and Minor  Repairs.

IV.Repairs   and completion  of Toilets.

V. Repairs  and construction  of Kitchen  Sheds.

Except    construction    of   ACRs   and    Compound   Walls    all    other    Nadu    Nedu components  are targeted   for  completion  by 12th June 2023.

The  following   activities   should   be attended   to  by  all the  Head  Masters  of  Phase-II Nadu Nedu Schools  to  ensure  proper  execution   and completion  of Nadu Nedu works.

•   All the  CPM (central   procurement  material)   items  should  be received  by the  Head Master  or his/her  authorized   representative   and two  Parent  Committee  members. Once the  Head Masters  gave  readiness  for  any CPM material   such  material   has to be accepted,   rejection   can be done  only  on account  of poor quality   or short  supply.

Flash...   Aided staff absorption into Government - Schedule released for counselling

•    Stage   wise   Ceiling  and  Roof  repairs  photos    must   be  captured   and  uploaded to STMS  by  HM,  from   his/her    login.

•    All  the   Central  Procurement   items   must   be  assembled   and   made   ready before   the re opening   of schools  ( i.e,  12.06.2023).

•    Centrally   procured   materials   such  as  Furniture,  Tiles   and  Electrical  fittings    should be properly   stored    and  assembly  of  equipment   should    be  done   under   the personal supervision of the   Head   Master.

•    All  the   HMs  should    ensure  that   no  or  minimum   discomfort   is caused  to students   on account  of  storagege   of  CPM  material   in  class  rooms.

•    HMs  shall   also  ensure  proper   safety    and  storage  of  CPM material   and  locally purchased   material.

•    Failure  to  comply  with   the   above   instructions    and  any  additional   cost  incurred   on logistics  due  to  negligence   or  non-compliance    of these   instructions    by Head Master  or  his  authorized   representative,    will  be  recovered   from   their  salaries, besides  initiating   disciplinary  action.

Hence,  all  the   Regional  Joint   Directors,   District   Educational   Officers  should ensure  that these   instructions    reach   all  the   Head   Masters  in  their   respective Districts   and  monitor   the compliance   of these   instructions.